Steam Blowing Out of MSL Piping in Power Plant

 

Blowing Out Steam Piping

Contents

1.         General ...............................................................................................................................

1.1        Safety and Noise Protection ................................................................................

2.         Blowing-Out Circuits ............................................................................................................

3.         Conditions for Blowing Out ..................................................................................................

3.1        Dynamic Pressure ..............................................................................................

3.2        Blow-Out Piping Design..................................................................................................

3.3        Blowing Gate Valve .............................................................................................................

4.         Blowing Out Operation ........................................................................................................

4.1        Duration of Each Blow...............................................................................................................

4.2        Number of Blows .................................................................................................................

4.3        Cooling Period ..................................................................................................

4.4        Blowing-Out Procedure..............................................................................................

5.         Cleanliness Assessments ...................................................................................................

5.1        Blowing Mirrors......................................................... ............................................................................

5.2        Acceptance Criteria .................................................................................................................................................

1. General

This recommendation defines the blowing-out requirements and cleanliness criteria specified by the manufacturer.

Blowing-out is carried out to remove rust, scale, coatings, dirt, and foreign objects from steam piping. This prevents blockage of the turbine inlet steam filter and damage to the turbine.

The turbine must never be started until the boiler and all steam piping leading to the turbine have been properly cleaned.

If blowing-out is not performed in accordance with this guideline, all risks are borne by the customer, and any resulting damage is excluded from warranty.

The manufacturer reserves the right to inspect the turbine before acceptance testing and, if necessary, to adjust guarantee values based on its condition. Any additional costs resulting from this inspection shall be borne by the customer.

If blowing-out is not carried out in accordance with this guideline, the customer must be formally informed in writing of the deviations and their consequences.


1.1 Safety and Noise Protection

Before blowing-out begins:

  • All steam lines must be insulated to prevent burns and fire hazards.
  • Danger areas must be clearly marked and secured.
  • Ensure no unauthorized personnel are present before each blow.
  • Noise protection measures are mandatory in accordance with regulations.

Noise can be reduced by:

  • Using a silencer, or
  • Discharging steam under water

The boiler or piping supplier is responsible for providing suitable noise-reduction measures.


2. Blowing-Out Circuits

Blowing-out is required for:

  • Boiler piping
  • Main and secondary steam lines
  • Bypass and pressure-reducing stations
  • Seal steam systems
  • Steam-jet air ejectors

Blowing-out is normally performed up to the valve casing or as close as possible.

A temporary blow-out pipe is connected to the steam pipe flange near the quick-action valve.

  • If blowing-out is performed through a quick-action valve, it must be removed.
  • If removal is not possible and the valve is welded, blowing-out may only be performed with manufacturer approval.

After completion, remove the temporary piping and install the final steam piping under clean conditions.

Sensitive components (valve seats, shafts, measuring orifices, etc.) should be removed from the blow-out circuit whenever possible.


3. Conditions for Blowing-Out

3.1 Dynamic Pressure

Adequate dynamic pressure is the most important factor for achieving high velocity of flow and, with these good levels of steam piping cleaning by blowing out. When carrying out blowing out, the dynamic pressure in the entire boiler and piping system must be greater than the subsequent maximum in full-load operation.

Below, we will use index A for the maximum through flow in full-load operation and index B for blowing out:



                

To ensure that the desired parameters of the mass flow rate are achieved, you should carry out an

estimate of the mass flow rate, if possible, by means of the operational measurement.

If possible, you should measure the pressure and the temperature for the calculation directly by the boiler outlet.

You should aim to achieve high steam conditions, since experience has shown that steam piping is not correctly cleaned until high temperatures have been reached.

The following empirical values are used to specify the pressure and temperature for blowing out:

  • Pressure: ≥ 50% of rated pressure
  • Temperature: At least 50 K superheat at rated pressure

3.2 Blow-Out Piping Design

  • Temporary blow-out piping should have a cross-section similar to the final piping.
  • Pipe supports must be designed for higher dynamic loads during blowing-out.
  • Permissible forces on turbine flanges must be respected.

The boiler or piping supplier is responsible for the design, supply, installation, and safety of the blow-out piping.


3.3 Blowing Gate Valve

A fast-opening blowing gate valve (opening time ≤ 30 seconds) is mandatory.

  • It must be installed upstream of the blow-out outlet
  • It improves cleaning efficiency and reduces blow-out time

The boiler or piping supplier must provide this valve.



4. Blowing-Out Operation

4.1 Duration of Each Blow

Each blow should last 1–2 minutes, depending on boiler capacity.

If the valve opening time exceeds 30 seconds, the blow duration must be extended accordingly.


4.2 Number of Blows

Blowing-out must continue until the required cleanliness level is achieved (see Section 5).


4.3 Cooling Period

After high-temperature blowing-out:

  • Allow piping to cool to near ambient temperature
  • Recommended cooling time: 5–6 hours (with insulation)

This prevents oxide layers from loosening after cleaning.


4.4 Blowing-Out Procedure

  1. Warm up piping and perform initial blows at moderate conditions to detect faults.
  2. Increase boiler output to specified blowing-out conditions.
  3. Open the blowing gate valve for 1–2 minutes.
  4. Repeat blowing 2–3 times.
  5. Reduce pressure, drain and clean the boiler evaporator.
  6. Cool the boiler using fans.
  7. On the following day, perform blowing-out at full pressure and temperature.

Steel mirrors are not installed during the first blows due to heavy contamination.


5. Cleanliness Assessment

5.1 Blowing Mirrors

Cleanliness is checked using steel mirrors, supplied by the boiler manufacturer.

  • Mirrors are installed after the blowing gate valve
  • A straight pipe section of at least 10 pipe diameters must be upstream


        

A mirror must be installed after each cooling period.


5.2 Acceptance Criteria

Cleanliness is acceptable when:

  1. Two consecutive blows show mirrors within limits
  2. After ≥12 hours cooling, two further consecutive blows also meet limits

Assessment limits (per 2500 mm²):

  • No strikes > 0.8 mm
  • Max 2 strikes > 0.4 mm
  • Max 10 strikes > 0.2 mm
  • Strikes < 0.2 mm must be evenly distributed

CAUTION:

              1.            For the first blowing process it is not recommended to use target plate whereas                                 for further cycles always the clean side of the target plate should be used.

2.            The pipe lines which are not pre-cleaned are expected to take blowing cycles twice than the pre-cleaned pipe lines.

Comments