1.6 Boiler Alkali Boil Out and Steam Blowing

 Stages of cleaning process of Boiler:

1. Cold and Hot water flushing 

  • Water temperature - 80 to 85 °C
  • Velocity - 0.2 to 1.5 m/sec
  • Flushing period - 15 to 20 min.

Flushing process will be repeated until outlet water conductivity reached 30 microsemen/cm.

Amonia (0.1%) and hydrazine (100ppm) then added in DM water, recirculated and drained to waste.

2. BOILER ALKALI BOIL OUT

PRECHECKS:-

1.   The boiler shall be ready in all aspects for steaming to the design capacity and steam parameters.

2.   Ensure drum internals including screen boxes are fixed and welding is completed before alkali boil out.

3.   Close all sampling points and instrument tapings at sources. Temporary sampling line for alkali boil out is recommended to avoid choking due to loose mill scale, debris, etc.

4.   Keep ready the following chemicals :-

    Trisodium phosphate (Na3PO4) 4000 ppm

The quantity for each boil out shall be estimated 4 x water volume of boiler (QM^3 x 4 Kgs)

    Sodium Carbonate (NaCO3) 4000 ppm.

The quantity for each boil out shall be estimated 4 x water volume of boiler (QM^3 x 4 Kgs)

 

PROCEDURE FOR ALKALI BOILOUT:-

1.       The boil out is to be carried out in three stages and fresh chemicals are to be charged before each stage.

2.       Fill the boiler with DM water (100 mm below manhole door level). Dissolve chemicals in DM water (use plastic containers) and pour into the drum through manhole door. (Do not put solids in drum).

3.       Light-up the boiler and raise the steam pressure gradually to 5 kg/cm² as per standard operating procedure and maintain the pressure for minimum 12 hours.

4.       Blow down once in two hours for 2 minutes to be given.

5.       Samples are to be taken for every two hours and analysis is to be carried out to determine the following.

1.  pH

2.  Total alkalinity

3.  Oil

6.       Ensure the pressure is maintained in the boiler for each stage of alkali boilout as follows :-

 

For 20 kg/cm² pressure boiler:

Duration

I Stage

5 Kg/cm²

12 Hours.

II Stage

7 Kg/cm²

12 Hours.

III Stage

10 Kg/cm²

12 Hours.

 

 

 

For 44 kg/cm² to 68 kg/cm² line pressure boilers

Duration

I Stage

7 Kg/cm²

12 Hours.

II Stage

10 Kg/cm²

12 Hours.

III Stage

20 Kg/cm²

12 Hours.

7.       Each stage of boiling can be terminated when the content of oil in the boiler water maintains a steady value. However final reading of oil should be 5-10 ppm. Decision for termination will be based on requirement for specific boiler.

8.       For each stage, after termination of boil out procedure, shut down the boiler and allow the unit to cool down gradually.

9.       Drain the boiler after the drum pressure reaches atmospheric pressure. Water jet shall be used to clean the headers for each stage.

10.   After complete draining of boiler, clean the complete unit by filling the water and drain it for at least one time for each stage.

Repeat the fill and drain until free from Alkalies.

The hand hole pipes of all headers preferably at bottom most point to be cut and inspected for any foreign material and cleaned using water jet.

11.   After inspection and cleaning re-weld the end caps and hydro test the boiler to working pressure.

 Acid cleaning procedure:

·       Remove drum internals.

·       Super Heater filled with ammonia and hydrazine (200ppm), pH should maintenance 10.

·       Add ammonia bi fluoride (0.5 w/v) and pressure 4 to 5 Kg/cm2.

·       Add acid  HCl ( 6% concentration) and pressure 3 to 4 Kg/cm2. Period 1 to 1.5 hours.

·       Test sample every 15 to 20 min.

·       Acid cleaning will completed when acid concentrations and iron content reached to constant value.

·       System is drained under N2 cover. N2 Capping protect metal surfaces from oxidation. Pressure should be 0.5 to 1.0 Kg/cm2.

1st stage passivation:

·       System filled with DM water at temperature 90 to 95 °C.

·       Add ammonia and hydrazine (200 ppm) and pH should be 10.

·       Circulation the water for 20 hours and system is drained out.

·       Drum and header inspection and cleaning.

2nd stage passivation:

·       Drum internals, mounting, fittings are fitted back.

·       Boiler filled up to normal operating level with 200 ppm hydrazine and pH 10.

·       Boiler lite up and pressure maintained 40 Kg/cm2 for 24 hours.

·       Ammonia and hydrazine injected to maintain residual hydrazine 25 ppm.

·       After 24 hours boiler cooled and at 80 °C system will drained.

STEAM BLOWING:

Steam blowing is an established practice for the purpose of physically removing any substance which remains deposited in the super heater and associated pipe lines. These substances are mainly scales and loose minerals that might have been entrapped during manufacture, storage and erection at site. Steam blowing is to be carried out only for boilers with super heater.

 

PRINCIPLE:

The principle of steam blowing is to give thermal shock and dislodge the scales. These scales will be subsequently driven out by the dynamic velocity of the expanding steam.

 

PROCEDURE: THE METHOD OF STEAM BLOWING IS AS BELOW:

               1.            Operate the boiler and raise the boiler pressure above 40 Kg/cm².

2.            At 40 kg/cm² steam pressure (line), slowly open the main steam stop valve by maintaining the drum level between 55% and 60%; blow the steam to atmosphere till the steam pressure drops down to 25 Kg/cm².

CAUTION: Do not allow the water to carry over (i.e. the stop valve should be opened in such a way) when the target plate is fixed since the water particles will give confusive results of the plate condition.

                3.            Slowly reduce the firing rate and slump the boiler. The main steam stop valve                                     shall be closed when the boiler pressure reaches 25 Kg/cm².

4.            After one hour, the boiler shall be restarted with one compartment and the bed temperature shall be maintained at 800°C.

The steam blowing shall be once again started when the pressure reaches 40 Kg/cm². By the above procedure, the scale adhering to the contours get cracked due to temperature difference and get removed to subsequent blows.

Temporary discharge piping which lead the steam to the atmosphere shall be welded down - stream of main steam line must be properly supported and anchored.

 

OPERATIONAL PRECAUTIONS:

1.            During steam blowing operation, the unit must be brought up much slower while   all equipments are checked and expansion movements are monitored closely.

2.            During blowing, water level in drum gauge glass may fluctuate very widely. Feed        regulating station must be checked for proper remote operation. Sufficient quantity of D.M water availability must be ensured.

 

                3.            Temporary discharge piping which should be at least equal to the diameter of                           piping to which it is connected must be well supported to withstand reaction                               forces during steam blowing.

                4.            Discharge piping should be so diverted that personnel and equipments are not                           endangered. The area should be cordoned off.

                5.            For welded type of NRV, the internals shall be removed to avoid damage during                                     blowing. Similarly the orifice plate or flow nozzle and thermowell shall be removed to avoid damage during blowing.

DETERMINATION OF STEAM CLEANLINESS:

                 1.            To determine the steam cleanliness MS or stainless steel target plate can be                 fixed at the exit of the blow pipe line.

                2.            The cleanliness shall be determined by locating the area of highest concentration             of the plate. Count the recognizable impressions i.e. 0.2 mm depth in 1 cm² located area.

                3.            The piping can be termed cleaned if less than two particles impressions of the                           considered 1 cm² area shown and if the remaining area does not show any                               individual rough impression.

 CAUTION:

                1.            For the first blowing process it is not recommended to use target plate whereas                                 for further cycles always the clean side of the target plate should be used.

2.            The pipe lines which are not pre-cleaned are expected to take blowing cycles twice than the pre-cleaned pipe lines.

Comments