11.0 Plant Residual Life Assessment

 Residual Life assessment (RLA) study

As per IBR regulation 391 A, the residual life of a running Boiler is assessed by ND tests.

For Boilers:-

1.

Operating above creep temperature (400 °C)

After 100000 Hrs of operation or 13.4 Years

2.

Operating below creep temperature

After 25 years of operation

 

Objective of RLA study as follows:

v  Prediction of impending failure of critical plant components resulting in enhanced safety, operation reliability, availability and maintainability.

v  Establishing life prediction, approach to enable repair, up gradation, replacement of necessary components and extension of remaining component life.

Types of tests:

A

Non Destructive Test

 

I

Visual Examination

 

II

Dimensional Measurement

 

III

Dye Penetration Test

 

IV

Magnetic Particle Inspection using wet non fluorescent method

Detection of surface and sub surface cracks/ discontinuity.

V

Ultrasonic Examination

Detection of sub surface cracks, loose bonding, material defects of any kind of discontinuity.

VI

Metallographic Replication by portable optical microscope

Assess the present micro structure condition of components.

VII

Hardness Measurement

 

VIII

Fibroscopic Inspection by means of miniature color video camera

Pitting or crack indication, scale of deposits, debris or loose parts.

B

Destructive Test

Metallurgical testing of tubes.

 

Test conducted at 10 MW thermal power plant:

 

BOILER

 

1

Steam drum and Mud drum

Visual, UT, MPT, LPI, Replication, Hardness, DIM, Deposit analysis

2

Water wall top and bottom header, Economizer I/L O/L header

Visual, UT, LPI, Hardness, DIM, Fibro optics inspection

3

Primary Super heater header

Visual, UT, LPI, Replication, Hardness, DIM

4

Final Super heater header

Visual, UT, LPI, Hardness, DIM, Fibro optics inspection, In situ metallography

5

Attemperator Header

Visual, UT, LPI, Replication, Hardness, DIM, Fibro optics inspection

6

Main steam pipe lines

Visual, UT, LPI, Replication, Hardness, DIM

7

Economizer tubes

Visual, DIM, Destructive test, Micro structure analysis

8

Prim. & Final super heater coils

Visual, DIM, Destructive test, Micro structure analysis, Hardness, Oxide scale thickness

9

Boiler bank tubes and water wall tubes

Visual, DIM, Destructive test, Micro structure analysis

10

Tubular Air Preheater

DIM

11

ID, FD and SA Fan

DPT

12

Feed water lines

Visual, UT, DPT, DIM

 

 

TURBINE

 

1

ESV

Visual, UT, MPI, DPT, Replication, Hardness

2

Throttle Valve

Visual, UT, MPI, DPT

3

Turbine casing, flange ligaments & inlet nozzle chamber

Visual, DIM, UT, MPI, DPT, Replication, Hardness

4

Diaphragm and stationary blade

Visual, DIM, MPI, DPT, Replication, Hardness

5

Parting plane fastners

Visual, MPI, DIM, Replication, Hardness

6

Gland casing

Visual, DIM, MPI

7

Turbine rotor forging, HP gland area, Journal, Disc

Visual, MPI, DPT, Replication, Hardness

8

Rotating blade, shrouds, Lacing wire & attachment

Visual, MPI, DPT, Replication, Hardness

9

Bearings

Visual, DIM, UT, DPT

10

Coupling Bolts

Visual, DIM, DPT

11

Condenser

Visual, UT, DPT

12

Generator shaft

UT, DPT

 

 

ELECTRICAL SYSTEM

 

1

Generator rotor winding

DCR, IR, PI, HI-POT, Step Voltage Test. TDT, CT, PD, ELCID

2

Generator stater bus duct and 11KV cable

IR, HVT, TDT, PD

3

Generator Rotor

IR, RIT, WRT, PI

4

LT motor

IR, DCR

5

Power Transformer

IR, PI, ECT, DCR, MBT, TDT, PD

6

Transformer Oil

BDV, Resistivity, Acidity, PPM, DGA,PSM

7

Bushing

TDT, CT

8

Auxiliary transformer

IR, PI, DCR

9

Current Transformer

IR, PI, DCR

10

Potential transformer 11 KV

IR, PI

11

LV Switch gear/ MCC

IR, HVT, CRT, Breaker open/close time, PRT

12

LV cables

IR

13

MV Switch gear

IR, CRT, Breaker open/close time, PRT

14

MV motors

IR, PI, TDT, WRT

 

 

ABBREVIATION

 

DCR

DC Resistance

 

IR

Insulation Resistance

 

PI

Polarization Index

 

TDT

Tan Delta Test

 

CT

Capacitance Test

 

CRT

Contact Resistance Test

 

RIT

Rotor Impedance Test

 

HVT

High Voltage Test

 

BDV

Break Down Voltage

 

MBT

Magnetic Balance Test

 

ECT

Excitation Current Test

 

PRT

Protective Relay Test

 

DGA

Dissolved Gas Analysis

 

PSM

Particle Size Measurement

 

MCR

Measurement of Contact Resistance

 

PD

Partial Discharge

 

HSVT

Hi-pot Step Voltage Test

 

WRT

Winding Resistance Test

 

 