Residual Life assessment (RLA) study
As per
IBR regulation 391 A, the residual life of a running Boiler is assessed by ND
tests.
For
Boilers:-
1. |
Operating above creep temperature (400 °C) |
After 100000 Hrs of operation or 13.4 Years |
2. |
Operating below creep
temperature |
After 25 years of
operation |
Objective of RLA study as follows:
v Prediction of impending failure of
critical plant components resulting in enhanced safety, operation reliability,
availability and maintainability.
v Establishing life prediction, approach
to enable repair, up gradation, replacement of necessary components and
extension of remaining component life.
Types of tests:
A |
Non
Destructive Test |
|
I |
Visual Examination |
|
II |
Dimensional
Measurement |
|
III |
Dye Penetration
Test |
|
IV |
Magnetic
Particle Inspection using wet non fluorescent method |
Detection
of surface and sub surface cracks/ discontinuity. |
V |
Ultrasonic
Examination |
Detection of sub
surface cracks, loose bonding, material defects of any kind of discontinuity.
|
VI |
Metallographic
Replication by portable optical microscope |
Assess
the present micro structure condition of components. |
VII |
Hardness
Measurement |
|
VIII |
Fibroscopic
Inspection by means of miniature color video camera |
Pitting
or crack indication, scale of deposits, debris or loose parts. |
B |
Destructive Test |
Metallurgical
testing of tubes. |
Test conducted at 10 MW thermal power
plant:
|
BOILER |
|
1 |
Steam drum and Mud
drum |
Visual, UT, MPT,
LPI, Replication, Hardness, DIM, Deposit analysis |
2 |
Water
wall top and bottom header, Economizer I/L O/L header |
Visual,
UT, LPI, Hardness, DIM, Fibro optics inspection |
3 |
Primary Super
heater header |
Visual, UT, LPI,
Replication, Hardness, DIM |
4 |
Final
Super heater header |
Visual,
UT, LPI, Hardness, DIM, Fibro optics inspection, In situ metallography |
5 |
Attemperator Header |
Visual, UT, LPI,
Replication, Hardness, DIM, Fibro optics inspection |
6 |
Main
steam pipe lines |
Visual,
UT, LPI, Replication, Hardness, DIM |
7 |
Economizer tubes |
Visual, DIM, Destructive
test, Micro structure analysis |
8 |
Prim.
& Final super heater coils |
Visual,
DIM, Destructive test, Micro structure analysis, Hardness, Oxide scale
thickness |
9 |
Boiler bank tubes
and water wall tubes |
Visual, DIM,
Destructive test, Micro structure analysis |
10 |
Tubular
Air Preheater |
DIM |
11 |
ID, FD and SA Fan |
DPT |
12 |
Feed
water lines |
Visual,
UT, DPT, DIM |
|
TURBINE |
|
1 |
ESV |
Visual, UT, MPI,
DPT, Replication, Hardness |
2 |
Throttle
Valve |
Visual,
UT, MPI, DPT |
3 |
Turbine casing,
flange ligaments & inlet nozzle chamber |
Visual, DIM, UT,
MPI, DPT, Replication, Hardness |
4 |
Diaphragm
and stationary blade |
Visual,
DIM, MPI, DPT, Replication, Hardness |
5 |
Parting plane
fastners |
Visual, MPI, DIM,
Replication, Hardness |
6 |
Gland
casing |
Visual,
DIM, MPI |
7 |
Turbine rotor
forging, HP gland area, Journal, Disc |
Visual, MPI, DPT,
Replication, Hardness |
8 |
Rotating
blade, shrouds, Lacing wire & attachment |
Visual,
MPI, DPT, Replication, Hardness |
9 |
Bearings |
Visual, DIM, UT,
DPT |
10 |
Coupling
Bolts |
Visual,
DIM, DPT |
11 |
Condenser |
Visual, UT, DPT |
12 |
Generator
shaft |
UT, DPT |
|
ELECTRICAL SYSTEM |
|
1 |
Generator rotor
winding |
DCR, IR, PI,
HI-POT, Step Voltage Test. TDT, CT, PD, ELCID |
2 |
Generator
stater bus duct and 11KV cable |
IR,
HVT, TDT, PD |
3 |
Generator Rotor |
IR, RIT, WRT, PI |
4 |
LT
motor |
IR, DCR |
5 |
Power Transformer |
IR, PI, ECT, DCR,
MBT, TDT, PD |
6 |
Transformer
Oil |
BDV,
Resistivity, Acidity, PPM, DGA,PSM |
7 |
Bushing |
TDT, CT |
8 |
Auxiliary
transformer |
IR, PI,
DCR |
9 |
Current Transformer |
IR, PI, DCR |
10 |
Potential
transformer 11 KV |
IR, PI |
11 |
LV Switch gear/ MCC |
IR, HVT, CRT,
Breaker open/close time, PRT |
12 |
LV
cables |
IR |
13 |
MV Switch gear |
IR, CRT, Breaker
open/close time, PRT |
14 |
MV
motors |
IR, PI,
TDT, WRT |
|
ABBREVIATION |
|
DCR |
DC Resistance |
|
IR |
Insulation
Resistance |
|
PI |
Polarization Index |
|
TDT |
Tan
Delta Test |
|
CT |
Capacitance Test |
|
CRT |
Contact
Resistance Test |
|
RIT |
Rotor Impedance
Test |
|
HVT |
High
Voltage Test |
|
BDV |
Break Down Voltage |
|
MBT |
Magnetic
Balance Test |
|
ECT |
Excitation Current
Test |
|
PRT |
Protective
Relay Test |
|
DGA |
Dissolved Gas Analysis |
|
PSM |
Particle
Size Measurement |
|
MCR |
Measurement of
Contact Resistance |
|
PD |
Partial
Discharge |
|
HSVT |
Hi-pot Step Voltage
Test |
|
WRT |
Winding
Resistance Test |
|
Comments